J-11. Partial Guaranteed Maximum Price - Balfour Beatty Construction, LLC - Temporary Serving Kitchen/Dining Room - Northeast High School, Oakland Park - Project No. P. 000230 (f.k.a. 1241-25-02) (C)  
August 27, 2008
Status: 
 
 

Quick Summary / Abstract
Approve the Partial Guaranteed Maximum Price (PGMP) in the amount of $929,083 submitted by Balfour Beatty Construction, LLC, for Northeast High School, New Stand-alone Kitchen/Cafeteria Building, Project No. P. 000230.

Project Consultant:  M.C. Harry & Associates

Scope:  Construct temporary serving kitchen/dining room.

The Board previously approved CM fees of $1,775,000 and Construction Budget of $8,874,705, for the total project including the construction of a new stand-alone kitchen/cafeteria building utilizing the food court concept. Before the construction of the new kitchen, the existing kitchen must be demolished as it occupies the space for the proposed new kitchen. The temporary serving kitchen/dining room must be in place prior to the demolition of the existing facility. The temporary facility will be used for the culinary arts program upon completion of the replacement kitchen/cafeteria building.
The Final GMP Manual is available for review at the Facilities and Construction Management Division.

The financial impact is $929,083.  This project is included in the District Educational Facilities Plan, Fiscal Years 2008-2009 to 2012-2013 for $10,813,861.   


Requested Action
Approve the Partial Guaranteed Maximum Price (PGMP) in the amount of $929,083 submitted by Balfour Beatty Construction, LLC, for Northeast High School, New Stand-alone Kitchen/Cafeteria Building, Project No. P. 000230.


Summary
Project Consultant:  M.C. Harry & Associates

Scope:  Construct temporary serving kitchen/dining room.

The Board previously approved CM fees of $1,775,000 and Construction Budget of $8,874,705, for the total project including the construction of a new stand-alone kitchen/cafeteria building utilizing the food court concept. Before the construction of the new kitchen, the existing kitchen must be demolished as it occupies the space for the proposed new kitchen. The temporary serving kitchen/dining room must be in place prior to the demolition of the existing facility. The temporary facility will be used for the culinary arts program upon completion of the replacement kitchen/cafeteria building.

The Final GMP Manual is available for review at the Facilities and Construction Management Division.

School Board Goals
Goal Three: Safety (2008-2011)


Financial Impact
The financial impact is $929,083.  This project is included in the District Educational Facilities Plan, Fiscal Years 2008-2009 to 2012-2013 for $10,813,861.   


Source of Additional Information
Denis Herrmann 754 321-1675



Associated File Attachments
Rationale (Files)  
ProjectFundsAllocation (Files)  
LetterfromBalfourBeattyConstruction,LLCdatedAugust5,2008 (Files)  
LetterfromM.C.Harry&AssociatesdatedJuly17,2008 (Files)  
CollaborationForm(CapitalBudget) (Files)  
ExecutedARF (Files)