1. Reduction of Retainage
Coral Glades High School–“JJJ”
New School
Project No. 3861-22-01
March 15, 2005 Status: Pending |
|||||||||||||||||||||
|
|||||||||||||||||||||
Quick Summary / Abstract
Approve the recommendation to reduce retainage now being held on the project from the Design-Builder, James B. Pirtle Construction Company, Inc., from $557,584 to $86,000. In accordance with School Board Policy 7005, the Facility and Construction Management Division is recommending that the retainage be reduced from 2% to less than 1%. The project has reached Substantial Completion. The amount of $86,000 is being withheld at this time pending final completion of the project. Subsequent to final completion, this project will be brought back to the Board for Final Acceptance and Release of Retainage. Funds being released totaling $471,584 are included in the Adopted District Educational Facilities Plan, 2004-2005 to 2008-2009. Requested Action Approve the recommendation to reduce retainage now being held on the project from the Design-Builder, James B. Pirtle Construction Company, Inc., from $557,584 to $86,000. Summary In accordance with School Board Policy 7005, the Facility and Construction Management Division is recommending that the retainage be reduced from 2% to less than 1%. The project has reached Substantial Completion. The amount of $86,000 is being withheld at this time pending final completion of the project. Subsequent to final completion, this project will be brought back to the Board for Final Acceptance and Release of Retainage. School Board Goals
Financial Impact Funds being released totaling $471,584 are included in the Adopted District Educational Facilities Plan, 2004-2005 to 2008-2009. Source of Additional Information Greg Boardman 754 321-1620 Associated File Attachments
|