The School Board of Broward County, Florida
Created : March 16, 2013 at 11:10 PM |
Meeting: Board Meeting : J. Facilities and Construction Management | |||||||||||||||||
2. Reduction of Retainage - Hawkes Bluff Elementary - Four (4) Classroom Modulars - Project No. 3131-21-01
August 05, 2003 Status: |
||||||||||||||||||
|
||||||||||||||||||
Quick Summary / Abstract
Approve the recommendation to reduce retainage now being held on the project from the Contractor, Padula and Wadsworth Construction, Inc., from $105,283 to $43,936. In accordance with Article 8.4 of the Agreement between The School Board of Broward County, Florida and Padula and Wadsworth Construction, Inc., the Facilities and Construction Management Division is recommending that the retainage be reduced. Construction of the project is presently 99% complete and 7% is being withheld at this time pending final accounting and close out documents. This project will be brought back to the Board for Final Release of Retainage. There is no additional financial impact to the district. Requested Action Approve the recommendation to reduce retainage now being held on the project from the Contractor, Padula and Wadsworth Construction, Inc., from $105,283 to $43,936. Summary In accordance with Article 8.4 of the Agreement between The School Board of Broward County, Florida and Padula and Wadsworth Construction, Inc., the Facilities and Construction Management Division is recommending that the retainage be reduced. Construction of the project is presently 99% complete and 7% is being withheld at this time pending final accounting and close out documents. This project will be brought back to the Board for Final Release of Retainage. School Board Goals
Financial Impact There is no additional financial impact to the district. Source of Additional Information David M. DeWald, Project Manager II, 954-760-7328 null Associated File Attachments
|