JJ-4. Change Order #1 - Cooper City High - Skanska USA Building, Inc. - Concurrent Phased Replacement - Project No. P.001539 (1931) (D)  
December 17, 2013
Status: 
Open Agenda
 
 

Quick Summary / Abstract
Approve Change Order #1, Cooper City High, Skanska USA Building, Inc., Concurrent Phased Replacement, Project No. P.001539, in the amount of $3,062,254, 207 days (155 compensable and 52 non-compensable).       

Change Order #1, $3,062,254, 207 days (155 compensable and 52 non-compensable)
Cooper City High
Skanska USA Building, Inc.
Concurrent Phased Replacement
Project No. P.001539

Refer to Exhibits 1 and 3 for detailed information.

The financial impact of this item is $3,062,254.  This is included in the $3,990,900 budget that was approved at the March 18, 2013, School Board Meeting.  


Requested Action
Approve Change Order #1, Cooper City High, Skanska USA Building, Inc., Concurrent Phased Replacement, Project No. P.001539, in the amount of $3,062,254, 207 days (155 compensable and 52 non-compensable).       


Summary
Change Order #1, $3,062,254, 207 days (155 compensable and 52 non-compensable)
Cooper City High
Skanska USA Building, Inc.
Concurrent Phased Replacement
Project No. P.001539

Refer to Exhibits 1 and 3 for detailed information.

School Board Goals
Goal 2: Continuous Improvement


Financial Impact
The financial impact of this item is $3,062,254.  This is included in the $3,990,900 budget that was approved at the March 18, 2013, School Board Meeting.  


Source of Additional Information
Sonja Coley 754 321-1520



Associated File Attachments
Executive Summary (Files)  
Previously approved item to approve funding, JJ-6 and Exhibit 1, 3/18/13 Board Meeting (Files)  
Change Order Analysis (Files)  
Change Order (Files)  
Change Order Summary to Date (Files)  
Collaboration Form (Capital Budget) (Files)  
ExecutedARF (Files)