JJ-4. Change Order #3 - Skanska USA Building, Inc. - Cooper City High - Concurrent Phased Replacement - Project No. P.000877 (D)
March 05, 2013 Status: Open Agenda |
||||||||||||||||||||||||
|
||||||||||||||||||||||||
Quick Summary / Abstract
Approve Change Order #3, for Skanska USA Building, Inc., Cooper City High , Concurrent Phased Replacement, Project No. P.000877, in the amount of $81,115, and 27days. Change Order #3, $81,115, 27 days Skanska USA Building, Inc. Cooper City High Concurrent Phased Replacement Project No. P.000877 Refer to Exhibits 1 and 3 for detailed information. The sources of funds are identified in the Adopted District Educational Facilities Plan, Fiscal Years 2012-2013 to 2016-2017. Requested Action Approve Change Order #3, for Skanska USA Building, Inc., Cooper City High , Concurrent Phased Replacement, Project No. P.000877, in the amount of $81,115, and 27days. Summary Change Order #3, $81,115, 27 days Skanska USA Building, Inc. Cooper City High Concurrent Phased Replacement Project No. P.000877 Refer to Exhibits 1 and 3 for detailed information. School Board Goals
Financial Impact The sources of funds are identified in the Adopted District Educational Facilities Plan, Fiscal Years 2012-2013 to 2016-2017. Source of Additional Information Sonja Coley 754 321-1639 Associated File Attachments
|