Meeting: Regular School Board Meeting :  JJ. Office of Facilities & Construction  
JJ-7. Change Order #11 - LeMartec Engineering and Construction Corporation - Lanier-James Education Center - Replacement School on New Location/Demolish Existing Facility - Project No. P.000077 (C)  
July 24, 2012
Status: 
 
 

Quick Summary / Abstract
Approve Change Order #11, LeMartec Engineering and Construction Corporation, Lanier-James Education Center, Replacement School on New Location/Demolish Existing Facility, Project No. P.000077.   

Lanier-James Education Center (SAAC); Change Order 011; Total:  $42,769, 28 days
Consultant Error  $3,271
Consultant Omission  $12,275
Owner Request  $27,223

The sources of funds are identified in the Adopted District Educational Facilities Plan, Fiscal Years 2011-2012 to 2015-2016.


Requested Action
Approve Change Order #11, LeMartec Engineering and Construction Corporation, Lanier-James Education Center, Replacement School on New Location/Demolish Existing Facility, Project No. P.000077.   


Summary
Lanier-James Education Center (SAAC); Change Order 011; Total:  $42,769, 28 days
Consultant Error  $3,271
Consultant Omission  $12,275
Owner Request  $27,223

School Board Goals
Goal Three: Safety (2008-2011)


Financial Impact
The sources of funds are identified in the Adopted District Educational Facilities Plan, Fiscal Years 2011-2012 to 2015-2016.


Source of Additional Information
Shelley Meloni 754 321-1610