Approve change orders as listed for various school projects, and approve an increase of $1,804,541, to the Capital Projects Reserve.   

Dania Elementary; Change Order 002; Total:  $1,382
Consultant Omission  $1,382

Dania Elementary; Change Order 007; Total:  $7,701  CREDIT
Owner Request  $7,701  CREDIT

Deerfield Beach Elementary; Change Order 006; Total:  $0  Time Extension
Owner Request  $0  Time Extension
Unforeseen Condition  $0  Time Extension

Hollywood Hills High; Change Order 204; Total:  $7,266
Consultant Error  $1,299
Consultant Omission  $5,967

Mirror Lake Elementary; Change Order 203; Total:  $1,796,840  CREDIT
Consultant Omission  $6,088
Owner Request  $1,802,928  CREDIT

Pines Lakes Elementary; Change Order 004; Total:  $12,267
Consultant Error  $4,097
Consultant Omission  $6,458
Owner Request  $2,653
Unforeseen Condition  $941  CREDIT

Financial Impact:   Dania Elementary - Project No.:  P.000011 $7,701 CREDIT;  Mirror Lake Elementary - Project No.: P.000357  $1,796,840 CREDIT.    The resulting financial impact shown above will increase the Capital Projects Reserve by $1,804,541.   There is no additional financial impact to the district for the remaining projects.




Requested Action
Approve change orders as listed for various school projects, and approve an increase of $1,804,541, to the Capital Projects Reserve.   




Summary
Dania Elementary; Change Order 002; Total:  $1,382
Consultant Omission  $1,382

Dania Elementary; Change Order 007; Total:  $7,701  CREDIT
Owner Request  $7,701  CREDIT

Deerfield Beach Elementary; Change Order 006; Total:  $0  Time Extension
Owner Request  $0  Time Extension
Unforeseen Condition  $0  Time Extension

Hollywood Hills High; Change Order 204; Total:  $7,266
Consultant Error  $1,299
Consultant Omission  $5,967

Mirror Lake Elementary; Change Order 203; Total:  $1,796,840  CREDIT
Consultant Omission  $6,088
Owner Request  $1,802,928  CREDIT

Pines Lakes Elementary; Change Order 004; Total:  $12,267
Consultant Error  $4,097
Consultant Omission  $6,458
Owner Request  $2,653
Unforeseen Condition  $941  CREDIT


School Board Goals
Goal Three: Safety (2008-2011)


Financial Impact
Financial Impact:   Dania Elementary - Project No.: P.000011 $7,701 CREDIT;  Mirror Lake Elementary - Project No.: P.000357 $1,796,840 CREDIT.    The resulting financial impact shown above will increase the Capital Projects Reserve by $1,804,541.   There is no additional financial impact to the district for the remaining projects.




Source of Additional Information
Jack Cooper 754 321-1607



Associated File Attachments
Change Order Analysis (Files)  
Change Orders (Files)  
Collaboration Form (Capital Budget) (Files)  
ExecutedARF (Files)