Meeting: Regular School Board Meeting :  J. Facilities and Construction Management  
4. Approve Final Construction Documents and Authorization to Advertise for Bids General Renovations Pines Lakes Elementary School, Pembroke Pines Project No. 2861-99-02
March 15, 2005
Status: Pending
 
 

Quick Summary / Abstract
Approve Final Construction Documents and Authorization to Advertise for Bids for Pines Lakes Elementary School, General Renovations, Project No. 2861-99-02.

Project Consultants:  GLE Associates, Inc.

Scope of Work:  Replace/upgrade air conditioning units, replace exhaust fans, replace cooling tower, replace/upgrade emergency generator, upgrade the fire alarm system, renovate restrooms to meet ADA standards, renovate kindergarten and elementary playgrounds to meet ADA standards, repair and automate the irrigation system, redesign the parent/bus drives, and perform off-site work to include a median cut and deceleration lane along Johnson Street.

The project Consultant’s Probable Cost of Construction (Exhibit 2) is $2,061,089.  Award of a contract may require $661,089 in additional funding.  Funds available for construction in Exhibit 1 total $1,4000,000.

Final Construction Documents are available for review at the Facilities and Construction Management Division.

Funds for this item are included in the Adopted District Educational Facilities Plan, Fiscal years 2004-05 to 2008-09, page 65.


Requested Action
Approve Final Construction Documents and Authorization to Advertise for Bids for Pines Lakes Elementary School, General Renovations, Project No. 2861-99-02.


Summary
Project Consultants:  GLE Associates, Inc.

Scope of Work:  Replace/upgrade air conditioning units, replace exhaust fans, replace cooling tower, replace/upgrade emergency generator, upgrade the fire alarm system, renovate restrooms to meet ADA standards, renovate kindergarten and elementary playgrounds to meet ADA standards, repair and automate the irrigation system, redesign the parent/bus drives, and perform off-site work to include a median cut and deceleration lane along Johnson Street.

The project Consultant’s Probable Cost of Construction (Exhibit 2) is $2,061,089.  Award of a contract may require $661,089 in additional funding.  Funds available for construction in Exhibit 1 total $1,4000,000.

Final Construction Documents are available for review at the Facilities and Construction Management Division.

School Board Goals
Goal 2 - All schools will have equitable resources.


Financial Impact
Financial Impact: Funds for this item are included in the Adopted District Educational Facilities Plan, Fiscal years 2004-05 to 2008-09, page 65.


Source of Additional Information
Denis Herrmann 754 321-1675