Meeting: Board Meeting :  J. Facilities and Construction Management  
8. Amend Professional Services Agreement/Supplemental Services - Broadview Elementary School - Kitchen & Cafeteria Replacement/Eight Classroom Addition - Project No. 0811-99-01
August 05, 2003
Status: 
 
 

Quick Summary / Abstract
Approve the amendment to the Professional Services Agreement dated January 5, 2002, between The School Board of Broward County, Florida and Architecture, Inc., by increasing the Supplemental Services fee by $15,000.

It is recommended that the Supplemental Services be increased on this project to cover expenses for cost estimating. As a result of additional appraisals for this project, it is requested that the Supplemental Services be increased from $26,680 to $41,680.

Any increase beyond $15,000 would require future Board action to modify the agreement.

The approved agreement for Supplemental Services is $26,680. This amendment will increase the Supplemental Services by an additional $15,000 to $41,680. This increase is within the project budget; therefore there is no additional impact to the district.


Requested Action
Approve the amendment to the Professional Services Agreement dated January 5, 2002, between The School Board of Broward County, Florida and Architecture, Inc., by increasing the Supplemental Services fee by $15,000.


Summary
It is recommended that the Supplemental Services be increased on this project to cover expenses for cost estimating. As a result of additional appraisals for this project, it is requested that the Supplemental Services be increased from $26,680 to $41,680.

Any increase beyond $15,000 would require future Board action to modify the agreement.

School Board Goals
Goal 2 - All schools will have equitable resources.


Financial Impact
The approved agreement for Supplemental Services is $26,680.  This amendment will increase the Supplemental Services by an additional $15,000 to $41,680.  This increase is within the project budget; therefore there is no additional impact to the district.


Source of Additional Information
Philip Kaufold, Project Manager II, (954) 765-6743 null