The School Board of Broward County, Florida
Created : May 10, 2014 at 10:45 PM
Meeting: Regular School Board Meeting :  JJ. Office of Facilities & Construction  
JJ-2. Change Order #1 - Nob Hill Elementary - Anatom Construction Services, Inc. - ADA Restroom Renovations - Project No. P.000463 (f.k.a. 2671-99-04) (D)  
May 06, 2014
Status: 
Open Agenda
 
 

Quick Summary / Abstract
Approve Change Order #1, Nob Hill Elementary, Anatom Construction Services, Inc., ADA Restroom Renovations, Project No. P.000463, in the amount of $5,319 - 77 days.

Change Order #1, $5,319 - 77 days
Nob Hill Elementary
Anatom Construction Services, Inc.
ADA Restroom Renovations
Project No. P.000463 (f.k.a. 2671-99-04)

Refer to Exhibits 1 and 3 for detailed information.

The source of funds is identified in the Adopted District Educational Facilities Plan, Fiscal Years 2013-2014 to 2017-2018.   


Requested Action
Approve Change Order #1, Nob Hill Elementary, Anatom Construction Services, Inc., ADA Restroom Renovations, Project No. P.000463, in the amount of $5,319 - 77 days.   


Summary
Change Order #1, $5,319 - 77 days
Nob Hill Elementary
Anatom Construction Services, Inc.
ADA Restroom Renovations
Project No. P.000463 (f.k.a. 2671-99-04)

Refer to Exhibits 1 and 3 for detailed information.

School Board Goals
Goal 2: Continuous Improvement


Financial Impact
The source of funds is identified in the Adopted District Educational Facilities Plan, Fiscal Years 2013-2014 to 2017-2018.


Source of Additional Information
Sonja Coley 754 321-1520



Associated File Attachments
Executive Summary (Files)  
Change Order Analysis (Files)  
Change Order (Files)  
Change Order Summary to date (Files)  
Collaboration Form (Files)