The School Board of Broward County, Florida
Created : September 07, 2013 at 05:25 AM
Meeting: Regular School Board Meeting :  JJ. Office of Facilities & Construction  
JJ-2. Change Order #2 Fort Lauderdale High - Kaufman Lynn Construction, Inc. - Remodeling/Renovations - Project No. P.000687 (D)  
July 23, 2013
Status: 
Open Agenda
 
 

Quick Summary / Abstract
Approve Change Order #2, Fort Lauderdale High, Kaufman Lynn Construction, Inc., Remodeling/Renovations, Project No. P.000687, in the amount of $68,401, 83 days.

Change Order #7, $68,401, 83days
Fort Lauderdale High
Kaufman Lynn Construction, Inc.
Remodeling / Renovations
Project No. P.000687

Refer to Exhibits 1 and 3 for detailed information.

The sources of funds are identified in the Adopted District Educational Facilities Plan, Fiscal Years 2012-2013 to 2016-2017.


Requested Action
Approve Change Order #2, Fort Lauderdale High, Kaufman Lynn Construction, Inc., Remodeling/Renovations, Project No. P.000687, in the amount of $68,401, 83 days.  


Summary
Change Order #7, $68,401, 83days
Fort Lauderdale High
Kaufman Lynn Construction, Inc.
Remodeling / Renovations
Project No. P.000687

Refer to Exhibits 1 and 3 for detailed information.

School Board Goals
Goal 2: Continuous Improvement


Financial Impact
The sources of funds are identified in the Adopted District Educational Facilities Plan, Fiscal Years 2012-2013 to 2016-2017.


Source of Additional Information
Sonja Coley 754 321-1639



Associated File Attachments
Executive Summary (Files)  
Change Order Analysis (Files)  
Change Order (Files)  
Change Order Summary to date (Files)  
Collaboration Form (Files)  
ExecutedARF (Files)