Meeting: Regular School Board Meeting : JJ. Office of Facilities & Construction | |||||||||||||||||||||||
JJ-1. Change Order #7 - Cooper City High - Skanska USA Building, Inc. - Concurrent Phased Replacement - Project No. P.000877 (D)
July 23, 2013 Status: Open Agenda |
||||||||||||||||||||||||
|
||||||||||||||||||||||||
Quick Summary / Abstract
Approve Change Order #7, Cooper City High, Skanska USA Building, Inc., Concurrent Phased Replacement, Project No. P.000877, in the amount of $76,922, -0- days. Change Order #7, $76,922, -0- days Cooper City High Skanska USA Building, Inc. Concurrent Phased Replacement Project No. P.000877 Refer to Exhibits 1 and 3 for detailed information. The sources of funds are identified in the Adopted District Educational Facilities Plan, Fiscal Years 2012-2013 to 2016-2017. Requested Action Approve Change Order #7, Cooper City High, Skanska USA Building, Inc., Concurrent Phased Replacement, Project No. P.000877, in the amount of $76,922, -0- days. Summary Change Order #7, $76,922, -0- days Cooper City High Skanska USA Building, Inc. Concurrent Phased Replacement Project No. P.000877 Refer to Exhibits 1 and 3 for detailed information. School Board Goals
Financial Impact The sources of funds are identified in the Adopted District Educational Facilities Plan, Fiscal Years 2012-2013 to 2016-2017. Source of Additional Information Sonja Coley 754 321-1639 Associated File Attachments
|