JJ-8. Change Order #2 - Balfour Beatty Construction, LLC - Parkway Middle - Phased Replacement - Project No. P.000133 (C)  
July 24, 2012
Status: 
 
 

Quick Summary / Abstract
Approve Change Order #2 for Balfour Beatty Construction, LLC, Parkway Middle, Phased Replacement, Project No. P.000133.   

Parkway Middle; Change Order 002; Total:  $0, 188 days
Owner Request  $0   

The sources of funds are identified in the Adopted District Educational Facilities Plan, Fiscal Years 2011-2012 to 2015-2016.


Requested Action
Approve Change Order #2 for Balfour Beatty Construction, LLC, Parkway Middle, Phased Replacement, Project No. P.000133.


Summary
Parkway Middle; Change Order 002; Total:  $0, 188 days
Owner Request  $0    

School Board Goals
Goal Three: Safety (2008-2011)


Financial Impact
The sources of funds are identified in the Adopted District Educational Facilities Plan, Fiscal Years 2011-2012 to 2015-2016.


Source of Additional Information
Shelley Meloni 754 321-1610



Associated File Attachments
Executive Summary (Files)  
Change Order Analysis (Files)  
Change Order (Files)  
Collaboration Form (Capital Budget) (Files)  
ExecutedARF (Files)