Meeting: Regular School Board Meeting :  JJ. Office of Facilities & Construction  
JJ-9. Payment of Contingency Use Directive No. 02 - Balfour Beatty Construction, LLC - Phased Replacement - Parkway Middle School, Fort Lauderdale - Project No. P.000133 (D)  
July 24, 2012
Status: 
Open Agenda
 
 

Quick Summary / Abstract
REVISED

Approve the payment of $181,577.16 as described by Contingency Use Directive Number 02, executed January 31, 2012.

Per the plans, a new electrical service was added to service all of the new buildings, and those existing buildings scheduled to remain in service after the completion of Phase II, during the construction of Phase I. In order to have all life-safety systems powered from a single source, existing buildings 1, 2, 3, 4, 22, and 24 were switched to the account for the new electric service in 2010. The Construction Manager at Risk, Balfour Beatty Construction, LLC, paid the entire electrical bill for this new service from November 15, 2010 until January 13, 2012, including the portion for existing buildings. This is not required by the contract and must be reimbursed.

The School Board of Broward County, Florida (SBBC) staff and an independent estimator have determined that $181,577 is the District's proportional share of the total electrical bill for the period in question.

The funds for payment of $181,577.16 are included in the Adopted District Educational Facilities Plan, fiscal years 2008-2009 to 2012-2013, page 155. will come from the District Utility Budget 2012-2013.


Requested Action
REVISED

Approve the payment of $181,577.16 as described by Contingency Use Directive Number 02, executed January 31, 2012.




Summary
Per the plans, a new electrical service was added to service all of the new buildings, and those existing buildings scheduled to remain in service after the completion of Phase II, during the construction of Phase I. In order to have all life-safety systems powered from a single source, existing buildings 1, 2, 3, 4, 22, and 24 were switched to the account for the new electric service in 2010. The Construction Manager at Risk, Balfour Beatty Construction,31 LLC, paid the entire electrical bill for this new service from November 15, 2010 until January 13, 2012, including the portion for existing buildings. This is not required by the contract and must be reimbursed.

SBBC staff and an independent estimator have determined that $181,577 is the District's proportional share of the total electrical bill for the period in question.



School Board Goals
Goal Three: Safety (2008-2011)


Financial Impact
The funds for payment of $181,577.16 are included in the Adopted District Educational Facilities Plan, fiscal years 2008-2009 to 2012-2013, page 155. will come from the District Utility Budget 2012-2013.




Source of Additional Information
Charles Ricks 754 321-1602



Associated File Attachments
ExecutiveSummary (Files)  
ContingencyUseDirectiveNo.02,datedJanuary 25, 2012 (Files)  
MEMO TO REVISE (Files)  
ExecutedARF (Files)