J-1. Change Orders (C)  
February 01, 2011
Status: 
 
 

Quick Summary / Abstract
Approve change orders as listed for various school projects, and approve an increase of $1,494,599 to the Capital Projects Reserve.  

Hollywood Hills High; Change Order 205; Total:  $4,785
Consultant Omission  $4,785

Miramar High; Change Order 001; Total:  $100,330
Consultant Error  $32,713
Owner Request  $30,382
Unforeseen Condition  $37,235

Oriole Elementary; Change Order 002; Total:  $7,386
Unforeseen Condition  $7,386

Palmview Elementary; Change Order 001; Total:  $8,994
Owner Request  $8,994

Village Elementary; Change Order 015; Total:  $1,494,929  CREDIT
Owner Request  $1,494,929  CREDIT
Unforeseen Condition  $0  Time Extension

Financial Impact: The resulting financial impact shown below will increase the Capital Projects Reserve by $1,494,599.  Miramar High - Project No.:  P.000336  $330; Village Elementary - Project No.:  P.000288  $1,494,929 CREDIT.  There is no additional financial impact to the district for the remaining projects.


Requested Action
Approve change orders as listed for various school projects, and approve an increase of $1,494,599 to the Capital Projects Reserve.  



Summary
Hollywood Hills High; Change Order 205; Total:  $4,785
Consultant Omission  $4,785

Miramar High; Change Order 001; Total:  $100,330
Consultant Error  $32,713
Owner Request  $30,382
Unforeseen Condition  $37,235

Oriole Elementary; Change Order 002; Total:  $7,386
Unforeseen Condition  $7,386

Palmview Elementary; Change Order 001; Total:  $8,994
Owner Request  $8,994

Village Elementary; Change Order 015; Total:  $1,494,929  CREDIT
Owner Request  $1,494,929  CREDIT
Unforeseen Condition  $0  Time Extension





School Board Goals
Goal Three: Safety (2008-2011)


Financial Impact
Financial Impact: The resulting financial impact shown below will increase the Capital Projects Reserve by $1,494,599.  Miramar High - Project No.:  P.000336  $330; Village Elementary - Project No.:  P.000288  $1,494,929 CREDIT.  There is no additional financial impact to the district for the remaining projects.