The School Board of Broward County, Florida
|
Meeting: Regular School Board Meeting : J. Facilities and Construction Management | |||||||||||||||||
J-1. Change Orders (C)
November 09, 2010 Status: |
||||||||||||||||||
|
||||||||||||||||||
Quick Summary / Abstract
Approve change orders as listed for various school projects, and approve an increase of $952,968 to the Capital Projects reserve. Banyan Elementary; Change Order 003; Total: $24,427 CREDIT Owner Request $24,427 CREDIT Banyan Elementary; Change Order 003; Total: $43,481 CREDIT Owner Request $43,481 CREDIT Beachside Montessori Village; Change Order 009; Total: $261,220 Consultant Error $31,036 Consultant Omission $5,095 Owner Request $37,509 Unforeseen Condition $187,580 Bethune, Mary M. Elementary; Change Order 002; Total: $30,734 CREDIT Owner Request $30,734 CREDIT Cresthaven Elementary; Change Order 004; Total: $43,481 CREDIT Owner Request $43,481 CREDIT Davie Elementary; Change Order 003; Total: $27,422 CREDIT Owner Request $27,422 CREDIT Drew, Charles Elementary; Change Order 004; Total: $43,481 CREDIT Owner Request $43,481 CREDIT Drew, Charles Elementary; Change Order 002; Total: $49,765 CREDIT Owner Request $49,765 CREDIT Driftwood Elementary; Change Order 003; Total: $5,475 CREDIT Owner Request $5,475 CREDIT Ely, Blanche High; Change Order 002; Total: $119,976 Owner Request $119,976 Forest Hills Elementary; Change Order 003; Total: $43,481 CREDIT Unforeseen Condition $43,481 CREDIT Forest Hills Elementary; Change Order 003; Total: $49,765 CREDIT Owner Request $49,765 CREDIT Hallandale Adult & Community Center; Change Order 002; Total: $38,195 CREDIT Owner Request $38,195 CREDIT Lanier-James Education Center (SAAC); Change Order 306; Total: $64,699 Owner Request $32,964 Unforeseen Condition $31,735 Larkdale Elementary; Change Order 002; Total: $24,427 CREDIT Owner Request $24,427 CREDIT North Lauderdale Elementary; Change Order 002; Total: $49,765 CREDIT Owner Request $49,765 CREDIT North Lauderdale Elementary; Change Order 003; Total: $24,427 CREDIT Owner Request $24,427 CREDIT Forman, Blanche (Nova) Elementary; Change Order 004; Total: $43,481 CREDIT Owner Request $43,481 CREDIT Palm Cove Elementary; Change Order 004; Total: $43,481 CREDIT Owner Request $43,481 CREDIT Park Ridge Elementary; Change Order 003; Total: $44,289 CREDIT Owner Request $44,289 CREDIT Park Ridge Elementary; Change Order 001; Total: $52,164 CREDIT Owner Request $52,164 CREDIT Park Ridge Elementary; Change Order 003; Total: $32,837 CREDIT Owner Request $32,837 CREDIT Pembroke Lakes Elementary; Change Order 002; Total: $49,765 CREDIT Owner Request $49,765 CREDIT Plantation High; Change Order 002; Total: $28,142 CREDIT Owner Request $28,142 CREDIT Riverglades Elementary; Change Order 003; Total: $43,481 CREDIT Owner Request $43,481 CREDIT Riverglades Elementary; Change Order 002; Total: $49,765 CREDIT Owner Request $49,765 CREDIT Riverland Elementary; Change Order 002; Total: $24,427 CREDIT Owner Request $24,427 CREDIT Sea Castle Elementary; Change Order 004; Total: $43,481 CREDIT Owner Request $43,481 CREDIT Seagull School; Change Order 003; Total: $11,117 Consultant Error $8,840 Consultant Omission $2,277 Silver Ridge Elementary; Change Order 003; Tot al: $24,427 CREDIT Owner Request $24,427 CREDIT Sunshine Elementary; Change Order 004; Total: $0 Time Extension Unforeseen Condition $0 Time Extension Tropical Elementary; Change Order 003; Total: $10,707 Consultant Omission $3,145 Owner Request $7,562 Westchester Elementary; Change Order 004; Total: $43,481 CREDIT Owner Request $43,481 CREDIT Westwood Heights Elementary; Change Order 002; Total: $49,765 CREDIT Owner Request $49,765 CREDIT Winston Park Elementary; Change Order 004; Total: $43,481 CREDIT Owner Request $43,481 CREDIT Winston Park Elementary; Change Order 002; Total: $49,765 CREDIT Owner Request $49,765 CREDIT Financial Impact: The resulting financial impact for the projects listed on the attached collaboration form (exhibit 3) will increase the Capital Projects reserve by $952,968. All credit items will go toward balancing the Capital Projects reserve this 2010-2011 school year. There is no additional financial impact to the district for the remaining projects. Requested Action Approve change orders as listed for various school projects, and approve an increase of $952,968 to the Capital Projects reserve. Summary Banyan Elementary; Change Order 003; Total: $24,427 CREDIT Owner Request $24,427 CREDIT Banyan Elementary; Change Order 003; Total: $43,481 CREDIT Owner Request $43,481 CREDIT Beachside Montessori Village; Change Order 009; Total: $261,220 Consultant Error $31,036 Consultant Omission $5,095 Owner Request $37,509 Unforeseen Condition $187,580 Bethune, Mary M. Elementary; Change Order 002; Total: $30,734 CREDIT Owner Request $30,734 CREDIT Cresthaven Elementary; Change Order 004; Total: $43,481 CREDIT Owner Request $43,481 CREDIT Davie Elementary; Change Order 003; Total: $27,422 CREDIT Owner Request $27,422 CREDIT Drew, Charles Elementary; Change Order 004; Total: $43,481 CREDIT Owner Request $43,481 CREDIT Drew, Charles Elementary; Change Order 002; Total: $49,765 CREDIT Owner Request $49,765 CREDIT Driftwood Elementary; Change Order 003; Total: $5,475 CREDIT Owner Request $5,475 CREDIT Ely, Blanche High; Change Order 002; Total: $119,976 Owner Request $119,976 Forest Hills Elementary; Change Order 003; Total: $43,481 CREDIT Unforeseen Condition $43,481 CREDIT Forest Hills Elementary; Change Order 003; Total: $49,765 CREDIT Owner Request $49,765 CREDIT Hallandale Adult & Community Center; Change Order 002; Total: $38,195 CREDIT Owner Request $38,195 CREDIT Lanier-James Education Center (SAAC); Change Order 306; Total: $64,699 Owner Request $32,964 Unforeseen Condition $31,735 Larkdale Elementary; Change Order 002; Total: $24,427 CREDIT Owner Request $24,427 CREDIT North Lauderdale Elementary; Change Order 002; Total: $49,765 CREDIT Owner Request $49,765 CREDIT North Lauderdale Elementary; Change Order 003; Total: $24,427 CREDIT Owner Request $24,427 CREDIT Forman, Blanche (Nova) Elementary; Change Order 004; Total: $43,481 CREDIT Owner Request $43,481 CREDIT Palm Cove Elementary; Change Order 004; Total: $43,481 CREDIT Owner Request $43,481 CREDIT Park Ridge Elementary; Change Order 003; Total: $44,289 CREDIT Owner Request $44,289 CREDIT Park Ridge Elementary; Change Order 001; Total: $52,164 CREDIT Owner Request $52,164 CREDIT Park Ridge Elementary; Change Order 003; Total: $32,837 CREDIT Owner Request $32,837 CREDIT Pembroke Lakes Elementary; Change Order 002; Total: $49,765 CREDIT Owner Request $49,765 CREDIT Plantation High; Change Order 002; Total: $28,142 CREDIT Owner Request $28,142 CREDIT Riverglades Elementary; Change Order 003; Total: $43,481 CREDIT Owner Request $43,481 CREDIT Riverglades Elementary; Change Order 002; Total: $49,765 CREDIT Owner Request $49,765 CREDIT Riverland Elementary; Change Order 002; Total: $24,427 CREDIT Owner Request $24,427 CREDIT Sea Castle Elementary; Change Order 004; Total: $43,481 CREDIT Owner Request $43,481 CREDIT Seagull School; Change Order 003; Total: $11,117 Consultant Error $8,840 Consultant Omission $2,277 Silver Ridge Elementary; Change Order 003; Total: $24,427 CREDIT Owner Request $24,427 CREDIT Sunshine Elementary; Change Order 004; Total: &nbs p;$0 Time Extension Unforeseen Condition $0 Time Extension Tropical Elementary; Change Order 003; Total: $10,707 Consultant Omission $3,145 Owner Request $7,562 Westchester Elementary; Change Order 004; Total: $43,481 CREDIT Owner Request $43,481 CREDIT Westwood Heights Elementary; Change Order 002; Total: $49,765 CREDIT Owner Request $49,765 CREDIT Winston Park Elementary; Change Order 004; Total: $43,481 CREDIT Owner Request $43,481 CREDIT Winston Park Elementary; Change Order 002; Total: $49,765 CREDIT Owner Request $49,765 CREDIT School Board Goals
Financial Impact Financial Impact: The resulting financial impact for the projects listed on the attached collaboration form (exhibit 3) will increase the Capital Projects reserve by $952,968. All credit items will go toward balancing the Capital Projects reserve this 2010-2011 school year. There is no additional financial impact to the district for the remaining projects. Source of Additional Information Jack Cooper 754 321-1607 Associated File Attachments
|