JJ-11. Total Program Management – Classroom Addition Program - James B. Pirtle Construction Co., Inc. - Final Guaranteed Maximum Price - Pines Lakes Elementary School (Group 4), Pembroke Pines - Project No. P.000683 (f.k.a. 2861-25-01) (OPEN AGENDA) (D)  
August 27, 2008
Status: 
Open Agenda
 
 

Quick Summary / Abstract
Approve the Final Guaranteed Maximum Price (GMP) in the amount of $4,746,605 for James B. Pirtle Construction Co., Inc., Pines Lakes Elementary School, 12 classrooms addition, Project No. P.000683. Approve an additional appropriation in the amount of $1,434,105 which will come from the Capital Projects Reserve.

The scope of this GMP includes the construction of 12 classrooms, administration suite, teacher planning suite, and custodial area.   

The Board previously approved TPM fees of $1,030,898 and a Construction Budget of $3,527,500.

The Final GMP Manual is available for review at the Facilities and Construction Management Division.

The financial impact is $4,746,605 including Cost of Work of $3,715,707 and TPM fees of $1,030,898.  This project is included in the  District Educational Facilities Plan, Fiscal Years 2008-2009 to 2012-2013 for $3,600,000.  There is an additional financial impact in the amount of $1,434,105 which will come from the Capital Projects Reserve.


Requested Action
Approve the Final Guaranteed Maximum Price (GMP) in the amount of $4,746,605 for James B. Pirtle Construction Co., Inc., Pines Lakes Elementary School, 12 classrooms addition, Project No. P.000683. Approve an additional appropriation in the amount of $1,434,105 which will come from the Capital Projects Reserve.


Summary
The scope of this GMP includes the construction of 12 classrooms, administration suite, teacher planning suite, and custodial area.   

The Board previously approved TPM fees of $1,030,898 and a Construction Budget of $3,527,500.

The Final GMP Manual is available for review at the Facilities and Construction Management Division.


School Board Goals
Goal Three: Safety (2008-2011)


Financial Impact
The financial impact is $4,746,605 including Cost of Work of $3,715,707 and TPM fees of $1,030,898.  This project is included in the  District Educational Facilities Plan, Fiscal Years 2008-2009 to 2012-2013 for $3,600,000.  There is an additional financial impact in the amount of $1,434,105 which will come from the Capital Projects Reserve.


Source of Additional Information
Denis Herrmann 754 321-1675



Associated File Attachments
LettersfromJamesB.PirtleConstructionCo.,Inc.andJamesR.Tucker,Inc. (Files)  
ProjectFundsAllocation (Files)  
CollaborationForm(CapitalBudget) (Files)  
ExecutedARF (Files)