JJ-2. Guaranteed Maximum Price - Pavarini Construction, Inc. - Kitchen/Cafeteria -Cooper City High School - Project No. P. 000385 (f.k.a. 1931-23-02 (OPEN AGENDA) (D)  
August 27, 2008
Status: 
Open Agenda
 
 

Quick Summary / Abstract
Approve the Guaranteed Maximum Price (GMP) in the amount of $13,250,000 submitted by Pavarini Construction, Inc., for Cooper City High School, Kitchen/Cafeteria, Project No. P. 000385.

Project Consultant: M.C. Harry & Associates, Inc.

Scope:  Construction of a single story kitchen/cafeteria building, a central utility building and general site improvements.

The Board previously approved CM fees of $2,275,000.

The Final GMP Manual is available for review at the Facilities and Construction Management Division.

The financial impact is $13,250,000 including the cost of work.  This project is included in the District Educational Facilities Plan, Fiscal Years 2008-2009 to 2012-2013 for $17,319,600. Based on the PFA, the budget for this project will be reduced by $1,184,351.


Requested Action
Approve the Guaranteed Maximum Price (GMP) in the amount of $13,250,000 submitted by Pavarini Construction, Inc., for Cooper City High School, Kitchen/Cafeteria, Project No. P. 000385.


Summary
Project Consultant: M.C. Harry & Associates, Inc.

Scope:  Construction of a single story kitchen/cafeteria building, a central utility building and general site improvements.

The Board previously approved CM fees of $2,275,000.

The Final GMP Manual is available for review at the Facilities and Construction Management Division.


School Board Goals
Goal Three: Safety (2008-2011)


Financial Impact
The financial impact is $13,250,000 including the cost of work.  This project is included in the District Educational Facilities Plan, Fiscal Years 2008-2009 to 2012-2013 for $17,319,600. Based on the PFA, the budget for this project will be reduced by $1,184,351.


Source of Additional Information
Denis Herrmann 754 321-1675



Associated File Attachments
ProjectFundsAllocation (Files)  
LetterfromPavariniConstruction,Inc.datedAugust6,2008 (Files)  
LetterfromMCHarry&AssociatesdatedAugust6,2008 (Files)  
CollaborationForm(CapitalBudget) (Files)  
ExecutedARF (Files)