13. J-13. ** Approve Award Of Contract - Traffic Improvements - Attucks Middle/Bethune Elementary Schools Project No. 0341-99-02 - Traffic Improvements - Croissant Park Elementary School Project No. 0221-21-02 - Traffic Improvements - Eagle Point Elementary School Project No. 3461-99-28 - Access Opening - Tequesta Trace Middle School Project No. 3151-21-05 (ADDED ITEM)
June 04, 2002
Status: 
 
 

Quick Summary / Abstract
Approve award of a construction contract for Attucks Middle/Bethune Elementary Project No. 0341-99-02 Traffic Improvements, Croissant Park Elementary Project No. 0221-21-02 Traffic Improvements, Eagle Point Elementary Project No. 3461-99-28 Traffic Improvements, Tequesta Trace Middle Project No. 3151-21-05 Access Opening, to the low bidder meeting the bid specifications, B & A Construction Services Group, Inc. The amount of the contract shall be $492,483, which includes the Base Bid and 1 Alternate.

Contractor: B & A Construction Services Group, Inc.

Consultant: Miller Legg & Associates, Inc.

Scope of Work: Project No. 0341-99-02 parking lot, off-site turn lane improvements and flasher design; Project No. 0221-21-02 furnish and install one cantilever mast arm school zone flasher with associated signing and striping, removal of one overhead spanwire reduced speed sign with associated electric; Project No. 3461-99-28 traffic improvements consisting of reconfiguring parent drop-off area; Project No. 3151-21-05 off-site turn-lane and minor parking lot improvements, tree removal and tree relocations.

Funds for Project No. 0341-99-02 are included in the Adopted District Facilities Work Program, Fiscal Years 2001-2002 to 2005-2006, Page 21 & 23, Project No. 0221-21-02 the CFR (Capital Funding Request) 2000-2001- control #33, Project No. 3461-99-28 Adopted District Facilities Work Program, Fiscal Years 1999-2000 to 2004-2005 Appendix E _Page 35 and Project No. 3151-21-05 CFR (Capital Funding Request) 1999-00. Additional funds will come from the Capital Projects Contingency Fund as follows: additional $258,512 for Attucks Middle School / Bethune Elementary School; additional $64,214 for Croissant Park Elementary School; additional $4,444 for Tequesta Trace Middle School. Total impact $327,170.


Requested Action
Approve award of a construction contract for Attucks Middle/Bethune Elementary Project No. 0341-99-02 Traffic Improvements, Croissant Park Elementary Project No. 0221-21-02 Traffic Improvements, Eagle Point Elementary Project No. 3461-99-28 Traffic Improvements, Tequesta Trace Middle Project No. 3151-21-05 Access Opening, to the low bidder meeting the bid specifications, B & A Construction Services Group, Inc.  The amount of the contract shall be $492,483, which includes the Base Bid and 1 Alternate.


Summary
Contractor: B & A Construction Services Group, Inc.

Consultant: Miller Legg & Associates, Inc.

Scope of Work: Project No. 0341-99-02 parking lot, off-site turn lane improvements and flasher design; Project No. 0221-21-02 furnish and install one cantilever mast arm school zone flasher with associated signing and striping, removal of one overhead spanwire reduced speed sign with associated electric; Project No. 3461-99-28 traffic improvements consisting of reconfiguring parent drop-off area; Project No. 3151-21-05 off-site turn-lane and minor parking lot improvements, tree removal and tree relocations.

School Board Goals
Goal 2 - All schools will have equitable resources.


Financial Impact
Funds for Project No. 0341-99-02 are included in the Adopted District Facilities Work Program, Fiscal Years 2001-2002 to 2005-2006, Page 21 & 23, Project No. 0221-21-02 the CFR (Capital Funding Request) 2000-2001- control #33, Project No. 3461-99-28 Adopted District Facilities Work Program, Fiscal Years 1999-2000 to 2004-2005 Appendix E _Page 35 and Project No. 3151-21-05 CFR (Capital Funding Request) 1999-00.  Additional funds will come from the Capital Projects Contingency Fund as follows:  additional $258,512 for Attucks Middle School / Bethune Elementary School; additional $64,214 for Croissant Park Elementary School; additional $4,444 for Tequesta Trace Middle School.  Total impact $327,170.   


Source of Additional Information
Denis Herrmann, Coordinator, Design and Construction Contracts, 760-7305 null