2. JJ-2. Total Program Management - Classroom Addition Projects - Approve Partial Guaranteed Maximum Price - Coral Park Elementary School, Coral Springs - Eagle Point Elementary School, Weston - Meadowbrook Elementary School, Fort Lauderdale - Sawgrass Elementary School, Sunrise - D. Stephenson Construction, Inc.(OPEN AGENDA) (ADDED ITEM) (D)  
June 06, 2006
Status: Pending
Open Agenda
 
 

Quick Summary / Abstract
Approve the Partial Guaranteed Maximum Price (GMP) in the amount of $2,656,976 for D. Stephenson Construction, Inc. and approve an additional appropriation of $2,061,976 from the capital projects reserve.

The scope of this GMP includes Classroom Additions at:  Coral Park Elementary School, 2 Classrooms; Eagle Point Elementary School, 4 Classrooms; Meadowbrook Elementary School, 2 Classrooms; and Sawgrass Elementary School, 3 Classrooms.

The Board previously approved TPM fees of $1,300,000 and a Construction Budget of $4,197,500.

The Final GMP Manual is available for review at the Facilities and Construction Management Division.

The financial impact is $ 2,032,976 for the Cost of Work. There is an additional financial impact of $2,061,976 that will be funded from the capital projects reserve.


Requested Action
Approve the Partial Guaranteed Maximum Price (GMP) in the amount of $2,656,976 for D. Stephenson Construction, Inc. and approve an additional appropriation of $2,061,976 from the capital projects reserve.


Summary
The scope of this GMP includes Classroom Additions at:  Coral Park Elementary School, 2 Classrooms; Eagle Point Elementary School, 4 Classrooms; Meadowbrook Elementary School, 2 Classrooms; and Sawgrass Elementary School, 3 Classrooms.
The Board previously approved TPM fees of $1,300,000 and a Construction Budget of $4,197,500.
The Final GMP Manual is available for review at the Facilities and Construction Management Division.

School Board Goals
Goal 2 - All schools will have equitable resources.


Financial Impact
The financial impact is $ 2,032,976 for the Cost of Work. There is an additional financial impact of $2,061,976 that will be funded from the capital projects reserve.