10. J-10. ** Selection of Design/Builder and Award of the Design/Build Agreement for High School "GGG" (Coconut Creek)RFP No. 2001-103 and Rejection of Base Cost Proposal and Alternate No. 2 North Area School of Choice (ADDED ITEM) (TIME CERTAIN 4:00 P.M.)
August 14, 2001
Status: 
 
 

Quick Summary / Abstract
Approve the selection of a Design/Builder and award a Design/Build Agreement based on Alternate No. 1 and Authorize the Deputy Superintendent to issue a Notice to Proceed to the Design/Builder selected by the Board on August 14, 2001 in response to RFP No. 2001_103, and approve the Project Funds Allocation including $1,323,564 in additional funding. It is also requested that The School Board of Broward County reject the Base Cost Proposal and Alternate No. 2 which are the Proposals for the combined facilities and the North Area School of Choice facility respectively.

The Design Criteria Package includes the option to award Alternate No. 1 for a single contract for High School "GGG." The single proposal received from James B. Pirtle Construction Co., Inc. Alternate No. 1 exceeds the available funding for the High School "GGG" project and if the project were awarded the Board would need to approve the additional funding.

This Agreement and Notice to Proceed will provide for the design and construction of High School "GGG" Coconut Creek, Florida.

Selected Design/Builder and respective project and contract amount is as follows:

James B. Pirtle Construction Co., Inc.
High School "GGG"
$27,000,000

The financial impact to the District is $1,323,564. Funds are identified in the Adopted District Facilities Work Program dated August 15, 2000 on pages 44 and 64.


Requested Action
Approve the selection of a Design/Builder and award a Design/Build Agreement based on Alternate No. 1 and Authorize the Deputy Superintendent to issue a Notice to Proceed to the Design/Builder selected by the Board on August 14, 2001 in response to RFP No. 2001_103, and approve the Project Funds Allocation including $1,323,564 in additional funding.  It is also requested that The School Board of Broward County reject the Base Cost Proposal and Alternate No. 2 which are the Proposals for the combined facilities and the North Area School of Choice facility respectively.


Summary
The Design Criteria Package includes the option to award Alternate No. 1 for a single contract for High School "GGG." The single proposal received from James B. Pirtle Construction Co., Inc. Alternate No. 1 exceeds the available funding for the High School "GGG" project and if the project were awarded the Board would need to approve the additional funding.

This Agreement and Notice to Proceed will provide for the design and construction of High School "GGG" Coconut Creek, Florida.

Selected Design/Builder and respective project and contract amount is as follows:

James B. Pirtle Construction Co., Inc.
High School "GGG"
$27,000,000

School Board Goals
Goal 2 - All schools will have equitable resources.


Financial Impact
The financial impact to the District is $1,323,564.  Funds are identified in the Adopted District Facilities Work Program dated August 15, 2000 on pages 44 and 64.  


Source of Additional Information
Denis Herrmann, Coordinator, Design & Construction Contracts 760-7305 null