Meeting: Regular School Board Meeting :  DD. Office of the Chief Auditor  
DD-1. Review of the Cypress Elementary School Project #1781-24-01/P000346 New Food Service Building, Renovations and Site Improvements (D)  
July 24, 2012
Status: 
Open Agenda
 
 

Quick Summary / Abstract
Receive Review of the Cypress Elementary School Project #1781-24-01/P000346 New Food Service Building, Renovations and Site Improvements.

This audit was performed at the request of Superintendent Robert W. Runcie, to review the Change Order listed in the January 18, 2012 School Board meeting, Agenda item JJ-8, for Cypress Elementary School, Item #011 in the amount of $198,900 for a 221 day delay that is being requested by the Construction Manager, (Hewett-Kier Construction, Inc.). The audit of the Cypress Elementary Change Order consisted of reviewing the Agreement Between Owner and Construction Manager, Professional Services Agreement, Board Agendas, Construction Meeting Minutes, emails, Consultant Reports, Policies & Procedures, project file documentation, site visits, interviews with District staff, Project Consultant (Architects), Construction Manager and various other individuals involved with the project. The objectives of our audit were to determine if the Construction Manager was entitled to a delay claim (compensation for Extended General Conditions) for 221 days at a cost of $198,900; to analyze the Change Order to determine if the number of days is reasonable, or if the Construction Manager is entitled to a different number of days, or if additional days should be granted without monetary compensation, to complete the project; and to provide management with recommendations to improve operations, based on our review of the Cypress Elementary Project.

It is the opinion of the Chief Auditor that the Cypress Elementary Project was not properly managed by the Construction Manager, Project Consultant or Facilities and Construction Management (F&CM) staff. The Office of the Chief Auditor, based on our review, recommends that F&CM deny any payment for delay claims (compensation for Extended General Conditions) for 221 days at a cost of $198,900. Subsequently, the Construction Manager is seeking an additional $77,350. We also recommend that F&CM should allow the Construction Manager 221 non-compensable days to complete the Cypress Elementary Project. We provided other recommendations to improve operations, based on our review.

The Audit Committee reviewed and approved this report for transmittal to the School Board during the Committee's May 17, 2012 meeting.

The source of funds to perform the Internal Audit Report was the General Fund budget allocation for the Office of the Chief Auditor.  There is no additional financial impact to the school district.


Requested Action
Receive Review of the Cypress Elementary School Project #1781-24-01/P000346 New Food Service Building, Renovations and Site Improvements.


Summary
This audit was performed at the request of Superintendent Robert W. Runcie, to review the Change Order listed in the January 18, 2012 School Board meeting, Agenda item JJ-8, for Cypress Elementary School, Item #011 in the amount of $198,900 for a 221 day delay that is being requested by the Construction Manager, (Hewett-Kier Construction, Inc.). The audit of the Cypress Elementary Change Order consisted of reviewing the Agreement Between Owner and Construction Manager, Professional Services Agreement, Board Agendas, Construction Meeting Minutes, emails, Consultant Reports, Policies & Procedures, project file documentation, site visits, interviews with District staff, Project Consultant (Architects), Construction Manager and various other individuals involved with the project. The objectives of our audit were to determine if the Construction Manager was entitled to a delay claim (compensation for Extended General Conditions) for 221 days at a cost of $198,900; to analyze the Change Order to determine if the number of days is reasonable, or if the Construction Manager is entitled to a different number of days, or if additional days should be granted without monetary compensation, to complete the project; and to provide management with recommendations to improve operations, based on our review of the Cypress Elementary Project.

It is the opinion of the Chief Auditor that the Cypress Elementary Project was not properly managed by the Construction Manager, Project Consultant or Facilities and Construction Management (F&CM) staff. The Office of the Chief Auditor, based on our review, recommends that F&CM deny any payment for delay claims (compensation for Extended General Conditions) for 221 days at a cost of $198,900. Subsequently, the Construction Manager is seeking an additional $77,350. We also recommend that F&CM should allow the Construction Manager 221 non-compensable days to complete the Cypress Elementary Project. We provided other recommendations to improve operations, based on our review.

The Audit Committee reviewed and approved this report for transmittal to the School Board during the Committee?s May 17, 2012 meeting.

School Board Goals
Goal Four: Innovation (2008-2011)
Goal Three: Safety (2008-2011)


Financial Impact
The source of funds to perform the Internal Audit Report was the General Fund budget allocation for the Office of  the Chief Auditor.  There is no additional financial impact to the School District.