J-17. Reduction of Retainage - Padula & Wadsworth Construction, Inc. - Phase Replacement II - North Andrews Gardens Elementary School, Ft. Lauderdale - Project No. P.000098 (f.k.a. 0521-95-01) (C)  
January 25, 2011
Status: 
 
 

Quick Summary / Abstract
Approve the recommendation to reduce retainage now being held on North Andrews Gardens Elementary School Phase Replacement II, Project No. P.000098, for Padula & Wadsworth Construction, Inc., from $218,938 to $49,482.

In accordance with School Board Policy 7005, the Facilities and Construction Management Department is recommending that the retainage be reduced from $218,938 to $49,482. The amount of $49,482 is being withheld pending final completion and the installation of smoke doors at Building #5 and #6 (second floor) by another Contractor and the credit change order for $48,482 for the deleted work. Therefore, the release of retainage to Padula & Wadsworth would be for $169,456.

This project will be brought back to the Board for Final Acceptance and Release of Retainage.

The funds being released totaling $169,456 are included in the Adopted District Educational Facilities Plan, Fiscal Years 2010-2011 to 2014-2015.


Requested Action
Approve the recommendation to reduce retainage now being held on North Andrews Gardens Elementary School Phase Replacement II, Project No. P.000098, for Padula & Wadsworth Construction, Inc., from $218,938 to $49,482.


Summary
In accordance with School Board Policy 7005, the Facilities and Construction Management Department is recommending that the retainage be reduced from $218,938 to $49,482. The amount of $49,482 is being withheld pending final completion and the installation of smoke doors at Building #5 and #6 (second floor) by another Contractor and the credit change order for $48,482 for the deleted work. Therefore, the release of retainage to Padula & Wadsworth would be for $169,456.

This project will be brought back to the Board for Final Acceptance and Release of Retainage.


School Board Goals
Goal Three: Safety (2008-2011)


Financial Impact
Greg Boardman 754 321-1620


Source of Additional Information
The funds being released totaling $169,456 are included in the Adopted District Educational Facilities Plan, Fiscal Years 2010-2011 to 2014-2015.



Associated File Attachments
retainagereducationcertification (Files)  
consentofsurety (Files)  
temporarycertificateofoccupancyletterdated110510 (Files)  
collaborationsignoffformcapitalbudget (Files)  
ExecutedARF (Files)