Approve the recommendations of the Superintendent indicated in Exhibit 1.

The Qualification Selection Evaluation Committee (QSEC) convened on January 12, 2011, to review Contractor Pre-Qualification Staff Application Review Executive Summaries received for the following contractors and makes the following recommendations to the Superintendent of Schools:

**Al Hill Plumbing Corporation - Issue Pre-qualification Re-Certification
**Decon Environmental & Engineering, Inc. (Asbestos) - Issue Pre-qualification Re-Certification
**Decon Environmental & Engineering, Inc. (General) - Issue Pre-qualification Re-Certification
Hewett-Kier Construction, Inc. - Issue Pre-qualification Re-Certification
Logictech Construction Group, LLC - Reject Appeal and Not Certify
M Space Holdings, LLC-  Issue Pre-qualification Re-Certification
**M.A.C. Construction, Inc. - Issue Pre-qualification Re-Certification
Merkury Development - Issue Pre-qualification Re-Certification
Roth Bros., Inc. - Issue Pre-qualification Re-Certification
TCS Group, Inc. - Issue Pre-qualification Re-Certification

*New Certification  **Certified M/WBE and/or SBE
                      
The Pre-Qualification Application reviews were conducted and the recommendations were determined in accordance with F.S. 1013.46, State Requirements for Educational Facilities and Board Policy 7003.  

Contractor Pre-Qualification Staff Application Review Executive Summaries are available for review at the Design & Construction Contracts Department.

There is no financial impact. This item is not affecting the overall budget; therefore, it does not require a collaboration form from the Capital Budget Department.


Requested Action
Approve the recommendations of the Superintendent indicated in Exhibit 1.


Summary
The Qualification Selection Evaluation Committee (QSEC) convened on January 12, 2011, to review Contractor Pre-Qualification Staff Application Review Executive Summaries received for the following contractors and makes the following recommendations to the Superintendent of Schools:

**Al Hill Plumbing Corporation - Issue Pre-qualification Re-Certification
**Decon Environmental & Engineering, Inc. (Asbestos) - Issue Pre-qualification Re-Certification
**Decon Environmental & Engineering, Inc. (General) - Issue Pre-qualification Re-Certification
Hewett-Kier Construction, Inc. - Issue Pre-qualification Re-Certification
Logictech Construction Group, LLC - Reject Appeal and Not Certify
M Space Holdings, LLC -  Issue Pre-qualification Re-Certification
**M.A.C. Construction, Inc. - Issue Pre-qualification Re-Certification
Merkury Development - Issue Pre-qualification Re-Certification
Roth Bros., Inc. - Issue Pre-qualification Re-Certification
TCS Group, Inc. - Issue Pre-qualification Re-Certification

*New Certification  **Certified M/WBE and/or SBE
                      
The Pre-Qualification Application reviews were conducted and the recommendations were determined in accordance with F.S. 1013.46, State Requirements for Educational Facilities and Board Policy 7003.  

Contractor Pre-Qualification Staff Application Review Executive Summaries are available for review at the Design & Construction Contracts Department.

School Board Goals
Goal Three: Safety (2008-2011)


Financial Impact
There is no financial impact. This item is not affecting the overall budget; therefore, it does not require a collaboration form from the Capital Budget Department.


Source of Additional Information
Denis Herrmann 754 321-1675



Associated File Attachments