JJ-5. Total Program Management – Classroom Addition Program - James B. Pirtle Construction Co., Inc. - Final Guaranteed Maximum Price - Embassy Creek Elementary School (Group 4), Cooper City - Project No. P.000686 (f.k.a. 3191-28-01) (OPEN AGENDA) (D)  
August 27, 2008
Status: 
Open Agenda
 
 

Quick Summary / Abstract
Approve the Final Guaranteed Maximum Price (GMP) in the amount of $5,418,523 for James B. Pirtle Construction Co., Inc., Embassy Creek Elementary School, 18 classrooms, Project No. P.000686. Approve an additional appropriation in the amount of $374,000 which will come from the Capital Projects Reserve.

The scope of this GMP includes the construction of 18 classrooms, administration suite, teacher planning suite, and custodial area.   

The Board previously approved TPM fees of $1,371,865 and a Construction Budget of $5,027,500.

The Final GMP Manual is available for review at the Facilities and Construction Management Division.

The financial impact is $5,418,523 including Cost of Work of $4,046,658 and TPM fees of $1,371,865.  There is an additional financial impact in the amount of $374,000 which will come from the Capital Projects Reserve.


Requested Action
Approve the Final Guaranteed Maximum Price (GMP) in the amount of $5,418,523 for James B. Pirtle Construction Co., Inc., Embassy Creek Elementary School, 18 classrooms, Project No. P.000686. Approve an additional appropriation in the amount of $374,000 which will come from the Capital Projects Reserve.


Summary
The scope of this GMP includes the construction of 18 classrooms, administration suite, teacher planning suite, and custodial area.   

The Board previously approved TPM fees of $1,371,865 and a Construction Budget of $5,027,500.

The Final GMP Manual is available for review at the Facilities and Construction Management Division.


School Board Goals
Goal 3 - All operations of the school system will demonstrate best practices while supporting student achievement.


Financial Impact
The financial impact is $5,418,523 including Cost of Work of $4,046,658 and TPM fees of $1,371,865.  There is an additional financial impact in the amount of $374,000 which will come from the Capital Projects Reserve.


Source of Additional Information
Denis Herrmann 754 321-1675



Associated File Attachments
LetterfromJamesB.PirtleConstructionCo.,Inc. (Files)  
ProjectFundsAllocation (Files)  
CollaborationForm(CapitalBudget) (Files)  
ExecutedARF (Files)