J-4. Pre-Qualification of Contractors - Approval of Application and Issuance of Certificates (C)  
August 27, 2008
Status: 
 
 

Quick Summary / Abstract
Approve the recommendations of the Superintendent and the Qualification Selection Evaluation Committee.

The Qualification Selection Evaluation Committee (QSEC) convened on July 16, 2008, to review Contractor Pre-Qualification Staff Application Review Executive Summaries received for the following contractors and makes the following recommendations to the Superintendent of Schools:

*Acies Construction, LLC – Issue Pre-Qualification Certification
*Asset Builders, LLC – Issue Pre-Qualification Certification
*Associated Craftsmen of America, Inc. – Issue Pre-Qualification Certification
Austin Commercial, LP – Issue Recommendation to Not Re-Certify
*Bovis Lend Lease, Inc. – Issue Pre-Qualification Certification
*BMA Construction, Inc. – Issue Pre-Qualification Certification  
Budget Construction Co., Inc. – Issue Recommendation to Not Certify
Cedars Electro-Mechanical, Inc. – Issue Recommendation to Not Increase Per Project & Aggregate Limts
*Close Construction, Inc. – Issue Pre-Qualification Certification
*C.S. Bensch, Inc. – Issue Pre-Qualification Certification
CSR Heavy Construction, Inc. – Issue Pre-Qualification Re-Certification
D. Stephenson Construction, Inc. – Issue Pre-Qualification Re-Certification
F. & L. Construction, Inc. – Issue Pre-Qualification Re-Certification
Gancedo Technologies, Inc. – Issue Pre-Qualification Re-Certification
*Garaventa USA, Inc. – Issue Pre-Qualification Certification
G.E.C. Associates, Inc. – Issue Pre-Qualification Re-Certification
*Hunter Construction Services, Inc. – Issue Pre-Qualification Certification
Inland Sealcoating, Inc. – Issue Pre-Qualification Re-Certification
*Intercounty Engineering, Inc. – Issue Pre-Qualification Certification
JCI International, Inc. – Issue Pre-Qualification Re-Certification
*M.L. Jones Construction Co. – Issue Pre-Qualification Certification  
*PCL Construction Services, Inc. – Issue Pre-Qualification Certification
Pence Sealcoating Corporation – Issue Pre-Qualification Re-Certification  
*Providian Construction Group, LLC – Issue Pre-Qualification Certification
Stiles Construction Company – Issue Pre-Qualification Re-Certification
*Tenex Enterprise, Inc. – Issue Pre-Qualification Certification
*The Roof Authority, Inc. – Issue Pre-Qualification Certification
Thermal Concepts, Inc. – Issue Pre-Qualification Re-Certification
Thornton Construction Co., Inc. – Issue Pre-Qualification Re-Certification
Tran Construction, Inc. – Issue Pre-Qualification Re-Certification
W.G. Mills, Inc. – Issue Pre-Qualification Re-Certification

*New Certification

The Pre-Qualification Application reviews were conducted and the recommendations were determined in accordance with F.S. 1013.46, State Requirements for Educational Facilities and Board Policy 7003.  

There is no financial impact to the district, therefore this item does not require a collaboration form from the Capital Budget Department.


Requested Action
Approve the recommendations of the Superintendent and the Qualification Selection Evaluation Committee.


Summary
The Qualification Selection Evaluation Committee (QSEC) convened on July 16, 2008, to review Contractor Pre-Qualification Staff Application Review Executive Summaries received for the following contractors and makes the following recommendations to the Superintendent of Schools:

*Acies Construction, LLC – Issue Pre-Qualification Certification
*Asset Builders, LLC – Issue Pre-Qualification Certification
*Associated Craftsmen of America, Inc. – Issue Pre-Qualification Certification
Austin Commercial, LP – Issue Recommendation to Not Re-Certify
*Bovis Lend Lease, Inc. – Issue Pre-Qualification Certification
*BMA Construction, Inc. – Issue Pre-Qualification Certification  
Budget Construction Co., Inc. – Issue Recommendation to Not Certify
Cedars Electro-Mechanical, Inc. – Issue Recommendation to Not Increase Per Project & Aggregate Limts
*Close Construction, Inc. – Issue Pre-Qualification Certification
*C.S. Bensch, Inc. – Issue Pre-Qualification Certification
CSR Heavy Construction, Inc. – Issue Pre-Qualification Re-Certification
D. Stephenson Construction, Inc. – Issue Pre-Qualification Re-Certification
F. & L. Construction, Inc. – Issue Pre-Qualification Re-Certification
Gancedo Technologies, Inc. – Issue Pre-Qualification Re-Certification
*Garaventa USA, Inc. – Issue Pre-Qualification Certification
G.E.C. Associates, Inc. – Issue Pre-Qualification Re-Certification
*Hunter Construction Services, Inc. – Issue Pre-Qualification Certification
Inland Sealcoating, Inc. – Issue Pre-Qualification Re-Certification
*Intercounty Engineering, Inc. – Issue Pre-Qualification Certification
JCI International, Inc. – Issue Pre-Qualification Re-Certification
*M.L. Jones Construction Co. – Issue Pre-Qualification Certification  
*PCL Construction Services, Inc. – Issue Pre-Qualification Certification
Pence Sealcoating Corporation – Issue Pre-Qualification Re-Certification  
*Providian Construction Group, LLC – Issue Pre-Qualification Certification
Stiles Construction Company – Issue Pre-Qualification Re-Certification
*Tenex Enterprise, Inc. – Issue Pre-Qualification Certification
*The Roof Authority, Inc. – Issue Pre-Qualification Certification
Thermal Concepts, Inc. – Issue Pre-Qualification Re-Certification
Thornton Construction Co., Inc. – Issue Pre-Qualification Re-Certification
Tran Construction, Inc. – Issue Pre-Qualification Re-Certification
W.G. Mills, Inc. – Issue Pre-Qualification Re-Certification

*New Certification

The Pre-Qualification Application reviews were conducted and the recommendations were determined in accordance with F.S. 1013.46, State Requirements for Educational Facilities and Board Policy 7003.


School Board Goals
Goal Three: Safety (2008-2011)


Financial Impact
There is no financial impact to the district, therefore this item does not require a collaboration form from the Capital Budget Department.


Source of Additional Information
Denis Herrmann 754 321-1675



Associated File Attachments
Contractor Pre-Qualification Staff Application Review Executive Summary (Files)  
ExecutedARF (Files)