The School Board of Broward County, Florida
Meeting: Regular School Board Meeting :  J. Facilities and Construction Management  
J-9. Change Orders
September 19, 2006
Status: 
 
 

Quick Summary / Abstract
Approve change orders as listed for various school projects, and an additional appropriation of $55,320 from Capital Projects Reserve.

Ely, Blanche High; Change Order 043; Total:  $10,584
Owner Request  $-16,961  CREDIT
Unforeseen Condition  $27,545

Hallandale Elementary; Change Order 013; Total:  $14,207
Consultant Error  $14,207

Lake Forest Elementary; Change Order 024; Total:  $21,164
Consultant Error  $3,101
Unforeseen Condition  $18,063

Pompano Beach High & North Area Admin.; Change Order 044; Total:  $9,365
Consultant Error  $9,365

Financial Impact: Ely, Blanche High - 0361-21-01 $10,584; Hallandale Elementary - 0593-99-02 $14,207;  Lake Forest Elementary - 0831-99-01 $21,164; Pompano Beach High & North Area Admin. - 0181-99-51 $9,365.  An additional financial impact of $55,320 will come from Capital Projects Reserve. There is no additional financial impact to the District for the remaining projects.




Requested Action
Approve change orders as listed for various school projects, and an additional appropriation of $55,320 from Capital Projects Reserve.



Summary
Ely, Blanche High; Change Order 043; Total:  $10,584
Owner Request  $-16,961  CREDIT
Unforeseen Condition  $27,545

Hallandale Elementary; Change Order 013; Total:  $14,207
Consultant Error  $14,207

Lake Forest Elementary; Change Order 024; Total:  $21,164
Consultant Error  $3,101
Unforeseen Condition  $18,063

Pompano Beach High & North Area Admin.; Change Order 044; Total:  $9,365
Consultant Error  $9,365



School Board Goals
Goal 2 - All schools will have equitable resources.


Financial Impact
Financial Impact: Ely, Blanche High - 0361-21-01 $10,584; Hallandale Elementary - 0593-99-02 $14,207;  Lake Forest Elementary - 0831-99-01 $21,164; Pompano Beach High & North Area Admin. - 0181-99-51 $9,365.  An additional financial impact of $55,320 will come from Capital Projects Reserve. There is no additional financial impact to the District for the remaining projects.






Source of Additional Information
Rick Ragland 754 321-1616



Associated File Attachments
Change Orders (Files)  
Collaboration Form (Files)  
ExecutedARF (Files)