Quick Summary / Abstract
REVISED
Approve change orders as listed for various school projects, and an additional appropriation of $196,815 will come from Capital Projects reserve.
Broadview Elementary; Change Order 006; Total: $65,358 $140,265
Consultant Error $61,977
Owner Request $3,381
Unforeseen Condition $74,907
King, Martin Luther Elementary; Change Order 009; Total: $20,056
Consultant Error $4,436
Unforeseen Condition $15,620
Meadowbrook Elementary; Change Order 013; Total: $5,891
Unforeseen Condition $5,891
Palm Cove Elementary; Change Order 015; Total: $21,528
Consultant Error $1,024
Owner Request $13,389
Unforeseen Condition $7,115
Perry, Annabel C. Elementary; Change Order 007; Total: $28,049
Consultant Error $26,852
Owner Request $1,197
Pine Ridge Education Center; Change Order 002; Total: $4,718
Unforeseen Condition $4,718
Piper High; Change Order 011; Total: $4,473
Owner Request $4,473
Plantation High; Change Order 030; Total: $-18,899
Unforeseen Condition $-18,899
Riverside Elementary; Change Order 004; Total: $3,896
Consultant Error $2,496
Unforeseen Condition $1,400
Whiddon-Rogers Adult Education Center; Change Order 004; Total: $108,204
Consultant Error $4,050
Owner Request $2,897
Unforeseen Condition $101,257
Financial Impact: King, Martin Luther Elementary - 1611-98-01 $20,056; Meadowbrook Elementary - 0761-99-01 $5,891 Palm Cove Elementary - 3311-98-01 $21,528; Perry, Annabel C. Elementary - 1631-99-01 $28,049; Pine Ridge Education Center - 0653-99-01 $4,718; Piper High - 1901-99-51 $4,473; Riverside Elementary - 3031-99-06 $3,896; Whiddon-Rogers Adult Education Center - 0452-21-01 $108,204. An additional financial impact of $196,815 will come from Capital Projects reserve. There is no additional financial impact to the District for the remaining projects.
Requested Action
REVISED
Approve change orders as listed for various school projects, and an additional appropriation of $196,815 will come from Capital Projects reserve.
Summary
Broadview Elementary; Change Order 006; Total: $65,358 $140,265
Consultant Error $61,977
Owner Request $3,381
Unforeseen Condition $74,907
King, Martin Luther Elementary; Change Order 009; Total: $20,056
Consultant Error $4,436
Unforeseen Condition $15,620
Meadowbrook Elementary; Change Order 013; Total: $5,891
Unforeseen Condition $5,891
Palm Cove Elementary; Change Order 015; Total: $21,528
Consultant Error $1,024
Owner Request $13,389
Unforeseen Condition $7,115
Perry, Annabel C. Elementary; Change Order 007; Total: $28,049
Consultant Error $26,852
Owner Request $1,197
Pine Ridge Education Center; Change Order 002; Total: $4,718
Unforeseen Condition $4,718
Piper High; Change Order 011; Total: $4,473
Owner Request $4,473
Plantation High; Change Order 030; Total: $-18,899
Unforeseen Condition $-18,899
Riverside Elementary; Change Order 004; Total: $3,896
Consultant Error $2,496
Unforeseen Condition $1,400
Whiddon-Rogers Adult Education Center; Change Order 004; Total: $108,204
Consultant Error $4,050
Owner Request $2,897
Unforeseen Condition $101,257
School Board Goals
|
Goal 2 - All schools will have equitable resources. |
|
Financial Impact
Financial Impact: King, Martin Luther Elementary - 1611-98-01 $20,056; Meadowbrook Elementary - 0761-99-01 $5,891 Palm Cove Elementary - 3311-98-01 $21,528; Perry, Annabel C. Elementary - 1631-99-01 $28,049; Pine Ridge Education Center - 0653-99-01 $4,718; Piper High - 1901-99-51 $4,473; Riverside Elementary - 3031-99-06 $3,896; Whiddon-Rogers Adult Education Center - 0452-21-01 $108,204. An additional financial impact of $196,815 will come from Capital Projects reserve. There is no additional financial impact to the District for the remaining projects.
Source of Additional Information
Rick Ragland 754 321-1616
Associated File Attachments
|
|