Meeting: Regular School Board Meeting :  JJ. Office of Facilities & Construction  
JJ-1. Approve Authorization to Proceed - Program Management Services - RFQ No. 2014-31-FC (See Items J-1 and JJ-2)(POSTPONED FROM 12/17/13 RSBM) (D)  
January 22, 2014
Status: 
Open Agenda
 
 

Quick Summary / Abstract
Approve the Authorization to Proceed in the amount of $437,592, and authorize the expenditure of up to $1,750,369.

This item approves the Authorization to Proceed ("ATP") (Exhibit 2) for Program Management Services in accordance with the terms and conditions of the Professional Services Agreement ("PSA") awarded to URS Corporation Southern and approved by the Board January 22, 2014.  This also authorizes the Office of Facilities & Construction to issue one or more ATPs for portions of the work included in this ATP as scheduled on page two of the ATP and to expend up to $1,750,369 for fees as negotiated and as delineated in Exhibit 2.  The work is related to the projects in Exhibit 3.

The Superintendent's Negotiating Committee met with URS Corporation Southern and negotiated fees in accordance with the recommendations of the Superintendent's Parameters Committee and Article 5 of the Program Management Services Agreement.  The purpose of this ATP is to commence Program Management Services for the Office of Facilities & Construction as delineated in Exhibit 2. Under the RFQ, the term of the Agreement is for one year with spending authority not to exceed $1,750,369 and may be renewed by Board approval in one-year periods for a maximum of three years and no more than $1,750,369 per year, as presented in J-1 (1/2214).

The financial impact is $437,592. The source of these funds is already identified in the Adopted District Educational Facilities Plan.


Requested Action
Approve the Authorization to Proceed in the amount of $437,592, and authorize the expenditure of up to $1,750,369.


Summary
This item approves the Authorization to Proceed ("ATP") (Exhibit 2) for Program Management Services in accordance with the terms and conditions of the Professional Services Agreement ("PSA") awarded to URS Corporation Southern and approved by the Board January 22, 2014.  This also authorizes the Office of Facilities & Construction to issue one or more ATPs for portions of the work included in this ATP as scheduled on page two of the ATP and to expend up to $1,750,369 for fees as negotiated and as delineated in Exhibit 2.  The work is related to the projects in Exhibit 3.

The Superintendent's Negotiating Committee met with URS Corporation Southern and negotiated fees in accordance with the recommendations of the Superintendent's Parameters Committee and Article 5 of the Program Management Services Agreement.  The purpose of this ATP is to commence Program Management Services for the Office of Facilities & Construction as delineated in Exhibit 2. Under the RFQ, the term of the Agreement is for one year with spending authority not to exceed $1,750,369 and may be renewed by Board approval in one-year periods for a maximum of three years and no more than $1,750,369 per year, as presented in J-1 (1/2214).

School Board Goals
Goal 2: Continuous Improvement


Financial Impact
The financial impact is $437,592. The source of these funds is already identified in the Adopted District Educational Facilities Plan.


Source of Additional Information
Shelley Meloni 754 321-1515 Denis Herrmann 754 321-0544



Associated File Attachments
Executive Summary (Files)  
Authorization to Proceed (Files)  
Project List (Files)  
Collaboration Form (Files)  
ExecutedARF (Files)